Builders in "DM GROUP" - do themselves ... NEBO (in the meaning SKY).
literally!
But the “hot” summer was not due to the weather at all . Every day at the construction site of the residential complex “NEBO” work was in full swing.
Confirmation of this is our results, which we will proudly share with you, dear customers:
1. Work on the facade glazing 3-15 floors has been finished.
2. Installation of a stained-glass window system of 3-15 floors has been completed.
3. We started glazing 16-18 floors.
4. The superstructure of 16.17.17 floors was completed.
5. The installation of tiles - 70%.
6. For section B, the screedand tiles are installed in apartments - 80%.
7. Work is underway on the installation of the exterior decoration of the facade from the V. Vernadsky street - 50%.
8. The foundation of the adjacent 3-level parking has been completed.
9. The carcass of the adjacent 3-level parking is being implemented - 30%.
10. Housing distribution of water - 50%.
11. The installation of storm risers and household sewage is carried out - 70%.
12. Proceeded to the installation of fences on the terraces.