Cold is not a problem. Great goals warm us!
Delmar knows for sure that tonic cold is a great motivator.
See it yourself by reading the construction report-diary on the Nebo residential complex.
-
3 floors of parking are completed for 60%.
-
Glazing of the facade of 3-14 floors is ongoing.
-
Installation of a stained-glass window system of 3-14 floors has started.
-
The laying of internal walls of aerated concrete of 3-14 floors is being carried out - 90%.
-
Preparatory work for the installation of elevators has started.
-
Work is underway on the arrangement of the 17th floor.
-
The ventilation system is being implemented - 60%.
-
Smoke removal shafts are made.
-
Installation of water supply and sewage systems is 50% completed.
-
Water supply is being carried out apartment by apartment - 10%.
-
Tiles plastering is underway.
-
Excavation work is underway for additional parking.
-
Exterior decoration of transitional balconies is being carried out.